| | CONSTRUCTION UPDATES | | A Building – RCC completed, 95% brickwork completed, internal gypsum in progress, electrical work in progress, plumbing work in progress, waterproofing work in progress, tiling work in progress. | | B Building – RCC completed, Brickwork completed, Internal gypsum completed, Waterproofing work completed, Flooring work completed, electrical work in progress, plumbing work in progress, door fixing in progress, painting in progress, lift works in progress. | | Project – Main Gate civil works completed, Compound wall completed, Transformer room finishing in progress, Club House RCC works in progress. | Outside the Project – The 24m DP road is partly completed with 8m two-lane road tarring done. The PMC drinking water and MNGL gas pipelines have been laid. |
| |
| | |
|
|